154KV Jinhae SS Indoor Airborne Construction Co., Ltd.
사업개요
공사명 | 154KV Jinhae SS Indoor Airborne Construction Co., Ltd. |
---|---|
공사내용 | 3rd floor above ground, 1st floor below ground, 2,403.24㎡ of total floor area, and civil engineering works (ground work, pavement, drainage, power) |
공사위치 | A member of Jinhae-gu, Changwon-si, Gyeongsangnam-do |
공사기간 | August 2021 to October 2023 |
발주처 | Korea Electric Power Corporation (KEPCO) Gyeongnam Headquarters |